You are managing a multi-year infrastructure project. Six months into execution, a local environmental group begins protesting against your project. They were not identified during the initial stakeholder analysis. What should you do next?
General Mindset 2

Quiz
•
Professional Development
•
Professional Development
•
Easy
Afghanistan Center
Used 2+ times
FREE Resource
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Refer back to the original stakeholder register and continue with the current stakeholder engagement plan.
Escalate the issue to the project sponsor and ask them to handle the stakeholder concerns.
Conduct a new stakeholder analysis and update the stakeholder register and engagement strategies.
Ignore the group since they were not identified as stakeholders during project initiation.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution phase of a complex IT project, a critical module experiences delays due to a third-party vendor issue. The client is not yet aware of this setback. What should the project manager do next?
Wait until the next scheduled status meeting to inform the client and include the update in the report.
notify the client and affected stakeholders with details of the delay and the mitigation plan.
Ask the vendor to resolve the issue quickly so there’s no need to escalate it to the client.
Update the issue log and hope the problem resolves before needing to alert stakeholders.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your team encounters an unexpected technical issue that may delay a key milestone by two weeks. After evaluating options, you find that accelerating the work using a specialized contractor will eliminate the delay but will increase project costs. What should you do?
Accept the two-week delay since quality should not be compromised to meet schedule.
Add the cost impact to the risk register and wait to see if further delays occur.
Proceed with hiring the specialized contractor to avoid delay, and submit a change request for the additional cost.
Escalate the issue to the project sponsor and let them decide which is more important—time or cost.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A senior stakeholder on your predictive project asks to change a key deliverable's specification after the scope has been baselined. What should the project manager do next?
Implement the change immediately to satisfy the stakeholder.
Tell the stakeholder that changes are not allowed once the scope is finalized.
Submit a formal change request for evaluation through the integrated change control process.
Add the change to the backlog for prioritization in the next sprint.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution phase of your project, a team member discovers a more efficient method for completing a recurring task. What should the project manager do to ensure this knowledge benefits future projects?
Wait until the project closes to document the new method in the final report.
Informally share the new approach with other team members and move on.
Update the lessons learned register and encourage team use across the current project.
Ask the PMO to evaluate the new method before recording it anywhere.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Midway through a predictive project, a stakeholder questions why a deliverable is being worked on now instead of later in the timeline. What should the project manager do first?
Adjust the schedule to meet the stakeholder’s expectation.
Consult the project management plan to confirm the sequencing of deliverables.
Ask the team to pause work on the deliverable until the issue is clarified.
Escalate the stakeholder concern to the change control board.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your team is facing difficulties integrating a new compliance module into the existing software system. None of the team members have experience with the specific regulatory requirements involved. What should you do next?
Ask the team to research the requirements online and continue working.
Raise a change request to remove the compliance module from the scope.
Engage a subject matter expert (SME) to provide guidance and ensure compliance.
Delay the work until a team member becomes comfortable with the integration.
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Agile Project Management

Quiz
•
Professional Development
10 questions
stakeholder interaction game.

Quiz
•
Professional Development
15 questions
SG20_Test_S8_CH10&13 Communications & Stakeholder

Quiz
•
Professional Development
13 questions
Agile Knowledge Quiz

Quiz
•
Professional Development
18 questions
Agile

Quiz
•
Professional Development
10 questions
Atoha PMP lesson 14

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
8 questions
Quiz Lesson 2 - Topic B (Form the Team)

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade