6035 Hazards

6035 Hazards

Vocational training

22 Qs

quiz-placeholder

Similar activities

Health and Safety Starter 1

Health and Safety Starter 1

KG

24 Qs

H&S and Principles

H&S and Principles

KG - University

20 Qs

JRCTC 2025 POC  FINAL EXAMS

JRCTC 2025 POC FINAL EXAMS

12th Grade

20 Qs

Health and Safety Regulations Part 2

Health and Safety Regulations Part 2

KG - University

19 Qs

Health and Safety in Building Services Engineering

Health and Safety in Building Services Engineering

12th Grade

20 Qs

Safety for Electricians (Electrical L1) Quiz

Safety for Electricians (Electrical L1) Quiz

12th Grade

18 Qs

Health and Safety Quiz

Health and Safety Quiz

2nd Grade

19 Qs

Construction Health and Safety Quiz

Construction Health and Safety Quiz

11th Grade

20 Qs

6035 Hazards

6035 Hazards

Assessment

Quiz

Construction

Vocational training

Hard

Created by

Chris Puddephatt

FREE Resource

22 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Hot works

What is the correct control measure?

·        Must have training before use

·        Place warning signs

·        Barrier off area of work

Wear correct PPE

·        Ensure tool is PAT tested

·        Check tool and cable for damage

·        Make sure you are using correct bit for task

Must have training before use

·        Place warning signs up

·        Mop up area

·        Warn people of hazard

Eliminate cause of spill and report

·        Use blowtorch in allocated area

·        Remove flammable items and use heat mats

·        Must have training before use

Have fire extinguisher in working area

Answer explanation

The correct control measures for hot works include using a blowtorch in an allocated area, removing flammable items, ensuring proper training, and having a fire extinguisher nearby to prevent fire hazards.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Wet floor

What is the control measure?

·        Place warning signs up

·        Mop up area

·        Warn people of hazard

Eliminate cause of spill and report

·        Assess the load

·        Plan and clear route

·        Bend knees when lifting

Straight back when lifting

·        Must have training before use

·        Check PAT test is in date

·        Make sure area is clear before use

Wear correct PPE

·        Plan activity to minimise crouching time

·        Have regular breaks

·        Strech regularly

Use support e.g knee pads

Answer explanation

To control the hazard of a wet floor, it is essential to place warning signs, mop up the area, warn people of the hazard, and eliminate the cause of the spill. These measures help prevent slips and ensure safety.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Power tools

What is the control measure?

·        Must have training before use

·        Check blades are sharp

·        Wear correct PPE & keep away from body

Put tools away safely and cover sharp edges

·        Assess the load

·        Plan and clear route

·        Bend knees when lifting

Straight back when lifting

·        Must have training before use

·        Place warning signs

·        Barrier off area of work

Wear correct PPE

·        Ensure tool is PAT tested

·        Check tool and cable for damage

·        Make sure you are using correct bit for task

Must have training before use

Answer explanation

The correct control measures for power tools include ensuring the tool is PAT tested, checking for damage, using the correct bit, and having training before use to ensure safety and proper operation.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Working at heights

What is the control measure?

·        Must have training before use

·        Check blades are sharp

·        Wear correct PPE & keep away from body

Put tools away safely and cover sharp edges

·        Use blowtorch in allocated area

·        Remove flammable items and use heat mats

·        Must have training before use

Have fire extinguisher in working area

·        Must have training before use & check safety tag is in date

·        Place warning signs

·        Barrier off area of work

Wear correct PPE

·        Assess the load

·        Plan and clear route

·        Bend knees when lifting

Straight back when lifting

Answer explanation

The correct control measures for working at heights include ensuring proper training and safety checks, placing warning signs, barring off work areas, and wearing appropriate PPE to minimize risks.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Trip hazard

What is the control measure?

·        Plan activity to minimise crouching time

·        Have regular breaks

·        Strech regularly

Use support e.g knee pads

·        Warn people of hazard

·        Tidy area of hazard

·        Place warning signs

Barrer off area and report

·        Place warning signs up

·        Mop up area

·        Warn people of hazard

Eliminate cause of spill and report

·        Use blowtorch in allocated area

·        Remove flammable items and use heat mats

·        Must have training before use

Have fire extinguisher in working area

Answer explanation

To control trip hazards, it's essential to warn people of the hazard, tidy the area, place warning signs, and barricade the area to prevent access. These measures help ensure safety and awareness.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Manual handling

What is the control measure?

·        Assess the load

·        Plan and clear route

·        Bend knees when lifting

Straight back when lifting

·        Must have training before use

·        Check PAT test is in date

·        Make sure area is clear before use

Wear correct PPE

·        Must have training before use

·        Check blades are sharp

·        Wear correct PPE & keep away from body

Put tools away safely and cover sharp edges

·        Place warning signs up

·        Mop up area

·        Warn people of hazard

Eliminate cause of spill and report

Answer explanation

To safely handle loads, it's essential to assess the load, plan a clear route, and use proper lifting techniques like bending knees and keeping a straight back. These measures reduce the risk of injury.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hazard

Operating machinery

What is the control measure?

·        Warn people of hazard

·        Tidy area of hazard

·        Place warning signs

Barrer off area and report

·        Must have training before use

·        Check blades are sharp

·        Wear correct PPE & keep away from body

Put tools away safely and cover sharp edges

·        Must have training before use

·        Check PAT test is in date

·        Make sure area is clear before use

Wear correct PPE

·        Use blowtorch in allocated area

·        Remove flammable items and use heat mats

·        Must have training before use

Have fire extinguisher in working area

Answer explanation

The control measures for operating machinery include ensuring proper training, checking the PAT test, keeping the area clear, and wearing the correct PPE to prevent accidents and ensure safety.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?