Critical Activities Identification Worksheet
Quiz
•
Construction
•
University
•
Practice Problem
•
Hard
hemyza budin
Used 3+ times
FREE Resource
Enhance your content in a minute
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Based on the tabulated data below, identify the critical activities?
A, B and D.
B, D and F.
C, E and G.
D, E and G.
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which of the following is categorized as an Activity on Arrow (AOA)?
I. Critical Path Method (CPM).
II. Precedence Diagram Method (PDM).
III. Program Evaluation Review Technique (PERT).
I and II.
I and III.
II and III.
I, II and III.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements does NOT represent an advantage of the Precedence Diagram technique?
Precedence diagrams are simple to draw, and easier to read and understand than other systems.
Dummy activities are not compulsory, therefore reducing the number of activities in a network.
The technique is not readily adaptable to both manual and computer programming.
It is easier to expand and modify the network, thus overlapping activities are more easily represented.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the following Precedence Diagram Method (PDM), B is
Earliest start.
Earliest finish.
Latest start.
Latest finish.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which statement best describes the following Arrow Network Diagram?
B & C follow A; D & E follow C; F follow B & D; G follow E & F.
B & C follow A; D & E follow B; E follows C; F follows D & E.
B & C follow A; D follow B; E & F follow C; G follows D & E & F.
D. B & C follow A; D & E follow B; E follows C; F follows D & E, G follow F.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the fourth stage in Maslow's Hierarchy of Needs?
Physiological Needs.
Self-Actualization.
Esteem.
Love and Belonging.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Free Float (FF) primarily serves the following purposes:
Determine which activities can be delayed without impacting the total float of the preceding activity.
Identify the activities which can be delayed without affecting the total float of succeeding activities.
Establish priorities.
Identify activities that can be delayed without impacting the total float of either the preceding or succeeding activities.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Construction
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
20 questions
christmas songs
Quiz
•
KG - University
20 questions
Holiday Trivia
Quiz
•
9th Grade - University
15 questions
Holiday Movies
Quiz
•
University
14 questions
Christmas Trivia
Quiz
•
3rd Grade - University
20 questions
Christmas Trivia
Quiz
•
University
8 questions
5th, Unit 4, Lesson 8
Lesson
•
KG - Professional Dev...
20 questions
Disney Trivia
Quiz
•
University