Critical Activities Identification Worksheet

Quiz
•
Construction
•
University
•
Hard
hemyza budin
Used 3+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Based on the tabulated data below, identify the critical activities?
A, B and D.
B, D and F.
C, E and G.
D, E and G.
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which of the following is categorized as an Activity on Arrow (AOA)?
I. Critical Path Method (CPM).
II. Precedence Diagram Method (PDM).
III. Program Evaluation Review Technique (PERT).
I and II.
I and III.
II and III.
I, II and III.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements does NOT represent an advantage of the Precedence Diagram technique?
Precedence diagrams are simple to draw, and easier to read and understand than other systems.
Dummy activities are not compulsory, therefore reducing the number of activities in a network.
The technique is not readily adaptable to both manual and computer programming.
It is easier to expand and modify the network, thus overlapping activities are more easily represented.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the following Precedence Diagram Method (PDM), B is
Earliest start.
Earliest finish.
Latest start.
Latest finish.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which statement best describes the following Arrow Network Diagram?
B & C follow A; D & E follow C; F follow B & D; G follow E & F.
B & C follow A; D & E follow B; E follows C; F follows D & E.
B & C follow A; D follow B; E & F follow C; G follows D & E & F.
D. B & C follow A; D & E follow B; E follows C; F follows D & E, G follow F.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the fourth stage in Maslow's Hierarchy of Needs?
Physiological Needs.
Self-Actualization.
Esteem.
Love and Belonging.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Free Float (FF) primarily serves the following purposes:
Determine which activities can be delayed without impacting the total float of the preceding activity.
Identify the activities which can be delayed without affecting the total float of succeeding activities.
Establish priorities.
Identify activities that can be delayed without impacting the total float of either the preceding or succeeding activities.
Create a free account and access millions of resources
Similar Resources on Wayground
Popular Resources on Wayground
10 questions
SR&R 2025-2026 Practice Quiz

Quiz
•
6th - 8th Grade
30 questions
Review of Grade Level Rules WJH

Quiz
•
6th - 8th Grade
6 questions
PRIDE in the Hallways and Bathrooms

Lesson
•
12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
15 questions
Subtracting Integers

Quiz
•
7th Grade
Discover more resources for Construction
15 questions
Let's Take a Poll...

Quiz
•
9th Grade - University
2 questions
Pronouncing Names Correctly

Quiz
•
University
34 questions
WH - Unit 2 Exam Review -B

Quiz
•
10th Grade - University
21 questions
Mapa países hispanohablantes

Quiz
•
1st Grade - University
10 questions
Transition Words

Quiz
•
University
5 questions
Theme

Interactive video
•
4th Grade - University
25 questions
Identifying Parts of Speech

Quiz
•
8th Grade - University
10 questions
Spanish Greetings and Goodbyes!

Lesson
•
6th Grade - University