PMP TEST

PMP TEST

53 Qs

quiz-placeholder

Similar activities

PROFPRAC 2 FINAL EXAM

PROFPRAC 2 FINAL EXAM

KG - University

50 Qs

MCC Info 1001 Information Literacy Assessment - Final

MCC Info 1001 Information Literacy Assessment - Final

9th - 12th Grade

50 Qs

Quizizz Center 1

Quizizz Center 1

KG - University

56 Qs

Section I: Listening

Section I: Listening

11th Grade

50 Qs

REMOVAL EXAMINATION

REMOVAL EXAMINATION

KG - University

50 Qs

C56-SE1908

C56-SE1908

KG - University

52 Qs

LATIHAN UJIAN SEKOLAH

LATIHAN UJIAN SEKOLAH

12th Grade

50 Qs

GA 931 Mid Term Exam 2023 3rd and 4th yr Cadet

GA 931 Mid Term Exam 2023 3rd and 4th yr Cadet

9th - 12th Grade

50 Qs

PMP TEST

PMP TEST

Assessment

Quiz

others

Hard

Created by

PMP TEST

FREE Resource

53 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 1 A team member has a sudden emergency that may last for several days. There are no other team members who can cover his tasks and job duties. What should the project manager do to address this concern?
A. Hold an emergency project team meeting to discuss the situation.
B. Ask the human resources (HR) manager for an external replacement.
C. Log the situation in the issue log.
D.Update the key stakeholders on the issue.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 2 A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project. What should the project manager do to address this concern?
A. Ask human resources (HR) to coordinate another activity.
B. Reassess the team situation and provide a proper solution.
C. Inform HR about the situation and ask for support.
D. Meet with the team to explain that conflicts must be addressed and solved.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 3 The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features. One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision. What should the project manager do?
A. Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future.
B. Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing.
C. Assume the responsibility for product releases making the final call on when something is ready for customer launch.
D. Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 4 During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a mini storage room. The sponsor insists on making this last-minute change, but they would like to avoid delays to the project. Which document should the project manager refer to first?
A. Change control plan.
B. Schedule management plan.
C. Scope management plan.
D. Cost management plan.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 5 Toward the end of a project the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A. Review the stakeholder engagement plan.
B. Review the quality management plan.
C. Review the requirements traceability matrix.
D. Review the work breakdown structure (WBS).

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 6 A project has been running successfully for 2 months. At a regular project meeting, the team raises several potential obstacles to future progress. The obstacles include vendor delivery performance, technical performance of a subsystem, and conflict with another division of the organization. What should the project manager do next?
A. Work with the team and others in the network to assess and prioritize the obstacles.
B. Engage with the external stakeholders and the other division of the organization to resolve the issues.
C. Escalate the obstacles to the project sponsor for assistance with resolution.
D. Determine a change response to identify and resolve the obstacles to move the project forward.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

# 7 A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do first?
A. Refer to the project charter.
B. Review the project resource matrix.
C. Assess the stakeholder register.
D.Update the communications management plan.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?