
PMP - PMI Study Hall - People Domain
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Hard
Deepak Kumar Meena
Used 1+ times
FREE Resource
Student preview

15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization is redesigning and relaunching a key product. The stakeholders are all company executives and want to ensure that the product launch will be a success.
What should the project manager do to ensure project success?
Implement a detailed communication management plan so that stakeholders are kept informed of the project status.
Communicate the critical nature of this project to the team and escalate any issues to the sponsor.
Ensure that all of the stakeholders attend the daily standups so that they can adjust the project as needed.
Work to identify and align performance indicators with the deliverable.
Answer explanation
Solution: D. Work to identify and align performance indicators with the deliverable.
In order to measure the successful delivery and completion of any initiative, it is critical to determine the performance indicators beforehand. The Project Manager can ensure project success by identifying & aligning the performance indicators with the deliverable.
Implementing a detailed communications management plan is incorrect as that is not the issue. Also, the stakeholder continues to receive communications. A project manager would not escalate to the project sponsor. All of the stakeholders do not attend the daily standups.
This question and rationale were developed in reference to:
O'Reilly Platform (No Date) //Objectives and key results - Chapter 5 - Managing with OKRs/ [Item]
| PMBOK Guide Sixth Edition (2018) PMI/PMI/Project Resource Management/350 [Item]
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In which stage of Tuckman's stages of team development do the team members begin to resolve conflicts effectively?
Forming
Storming
Norming
Performing
Answer explanation
Solution: C. Norming
Following the conflict of the storming phase, the team learns to work more effectively in the norming phase, including resolving conflicts. Norming is the correct choice. Norming is the stage at which the project team starts to function as a collective body. At this point, project team members know their places on the team and how they relate to and interface with all the other members. They are starting to work together. There might be some challenges as work progresses, but these issues are resolved quickly, and the project team moves into action.
Effective team conflict resolution skills are not present in the forming and storming stages. They are well developed in the performing stage, but the question asks at which stage they begin to arise.
The other options are incorrect.
The forming stage is when the project team first comes together. Members get to know each other’s names, position on the project team, skill sets, and other pertinent background information. This might occur in the kickoff meeting.
During the storming stage, project team members jockey for positions on the team. This phase is where people’s personalities, strengths, and weaknesses start to come out. There might be some conflict or struggle as people figure out how to work together. Storming might go on for some time or pass relatively quickly.
At the performing stage, the project team becomes operationally efficient. This is the mature project team stage. Project teams that have been together for a while are able to develop synergy. By working together, project team members accomplish more and produce a high-quality product.
This question and rationale were developed in reference to:
https://www.pmi.org/learning/library/best-practices-virtual-project-teams-6038 [Item Stage 3 – Norming: In this stage, the team is working together more effectively. Each member has found his or her place on the team and they are following processes and procedures. They support each other and problem solve and resolve conflicts effectively, with guidance from the team leader as necessary, to ensure the project keeps moving in the right direction. Technology is used effectively and efficiently to help the virtual team stay connected.]
PMBOK Guide Seventh Edition (2022) /// [4.2.6 PROJECT TEAM DEVELOPMENT MODELS]
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a project's execution phase, two stakeholders complain that they receive insufficient information on the project's status. The stakeholders have been included in the regular status meetings, and status reports are being shared with them.
Why should the project manager meet with these stakeholders?
To gather data on the issue in order to update the issue log.
To determine what information they are lacking and develop an understanding of their communication needs.
Send the stakeholders copies of the Emails previously sent to prove that they are included in the project's communications plan.
To develop a better working relationship with these stakeholders in order to prioritize and rank their requirements.
Answer explanation
Solution: B. To determine what information they are lacking and develop an understanding of their communication needs.
Since the stakeholders are already included in the status meetings and status reports, the project manager should meet with them one on one to understand what their additional communication needs are.
Managing Stakeholder Engagement involves activities such as managing stakeholder expectations through proper and accurate communications.
There is no issue that needs to be updated in the issue log as the stakeholders are being provided with all the required details. Emails are not working, sending "proof" does not address the issue.
This question and rationale were developed in reference to:
Fundamentals of Technology Project Management, 2nd Ed (2015) Colleen Garton, Erika McCulloch/Mc Press/14/454 [Item]
| Project management : A Systems Approach to Planning, Scheduling, and Controlling (2013) Harold Kerzner/John Wiley/8402-8522/ [Item]
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager needs to hire suppliers for an international project that has a performance period of several years. The project manager needs to allow for conditions such as changes in inflation rates.
What type of contract should the project manager use?
Time and material (T&M)
Cost plus fixed fee (CPFF)
Cost plus incentive fee (FPIF)
Fixed price with economic price adjustment (FPEPA)
Answer explanation
Solution: D. Fixed price with economic price adjustment (FPEPA)
The FP-EPA contract type is used whenever the seller’s performance period spans a considerable period of years, or if the payments are made in a different currency. It is a fixed-price contract, but with a special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes or cost increases (or decreases) for specific commodities.
All other options don't account for the inflation adjustment.
This question and rationale were developed in reference to:
e-Reads (No Date) ///The New Dynamic Project Management: Winning Through the Competitive Advantage, 2nd Edition - Chaper 14 - Procurement and Contract Management 14.4.4 Types of Contracts and Pricing Arrangements [Item]
| PMBOK® Guide--Fifth Edition (5th) PMI/PMI//Chapter 12 - Project Procurement Management - 12.1.1.9 Organizational Process Assets - Page 362-364 [Item]
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Team members express frustration because their functional manager does not listen to their opinions. They seem reluctant to devote themselves to the remainder of the project.
What should the project manager do?
Demonstrate support for the team by discussing their goals and beliefs.
Break the remaining work into smaller tasks and divide the tasks among the team.
Ask the team to prioritize the tasks remaining in the project.
Discuss the team's concerns with the functional manager.
Answer explanation
Solution: A. Demonstrate support for the team by discussing their goals and beliefs.
The primary goal of a project manager in relation to the project team is to ensure that the team has the time and resources to do their job and to remove any barriers they may encounter. By standing up for the team's beliefs the project manager is demonstrating their support for the team.
Breaking the remaining work into smaller task, dividing the tasks and asking the team to prioritize the task will not solve the frustration the team members are facing.
Discussing with team's concerns with the functional manager may not help to resolve the motivation of the team members to focus and complete the remainder of the project.
This question and rationale were developed in reference to:
Fundamentals of Technology Project Management, 2nd Ed (2012) ///24 [Item]
| Fundamentals of Technology Project Management, 2nd Ed (2015) Colleen Garton, Erika McCulloch/Mc Press/16/527 [Item]
| Information Technology Project Management, 7th Ed. (2015) Kathy Schwalbe/Schwalbe/9/391 [Item]
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project's statement of work (SOW) requires that the project be delivered in nine months. The project manager believes that the timeline is not realistic.
What should the project manager do?
Involve the change control board (CCB) in the Perform Integrated Change Control process
Submit a written request to the project sponsor for additional resources and budget
Meet with subject matter experts (SMEs) and the project sponsor to set expectations
Negotiate a new timeline with the project sponsor
Answer explanation
Solution: C. Meet with subject matter experts (SMEs) and the project sponsor to set expectations
If a project timeline is not realistic, then the project manager needs to provide the proof to the sponsor so that a realistic expectation can be set. The SMEs can provide that information and allow the sponsor to decide on a course of action.
The Change Control Board evaluates and approves additions or deletions of scope. A written request for additional resources and negotiating a new timeline could be an approach, but not the first thing one would do.
This question and rationale were developed in reference to:
PMBOK® Guide--Fifth Edition (No Date) PMI/PMI/4/71 [Item]
| Project management : A Systems Approach to Planning, Scheduling, and Controlling (2009) Harold Kerzner/John Wiley/11/521 [Item]
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The owner of a consulting company initiates a project to expand the number of services the company provides. The company has a competitive advantage, outstanding expertise, and an excellent reputation. The executive team wants to evaluate and rank criteria such as uncertainty and valuation regarding the addition of these new services.
Which technique should the project manager use to help the company make this evaluation?
Cause-and-effect diagram
Forecasting
Multicriteria decision analysis
Risk assessment matrix
Answer explanation
Solution: C. Multicriteria decision analysis
The correct answer is multicriteria decision analysis which is used to evaluate multiple criteria which could have a negative or positive impact. This would allow the executives to evaluate and prioritize the implementation of new services. Cause and effect diagrams are used for root cause analysis, forecasting is used for cost or schedule control, risk register contains identified risks and their response.
This question and rationale were developed in reference to:
Fundamentals of Technology Project Management, 2nd Ed (2015) Colleen Garton, Erika McCulloch/Mc Press//137 [Item]
| PMBOK Guide Sixth Edition (2018) ///5.2.2.4 DECISION MAKING [Item]
| The Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right (2004) Tom Kendrick/AMACOM//173 [Item]
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade