Project Management Quiz
Authored by Training Pusilkom
Other
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?
Weighing system
Screening system
Inspection and audits
Independent estimate
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager and team have decided to hire a contractor to complete building out the remaining section of the datacenter. They have the requirements listed in detail and would like to use a contract that would present the smallest amount of risk to the project. The project team members would like to purchase the materials themselves since there are very familiar with the work. What contract is best for this project?
Cost plus contractor fee
Cost plus project fee
Time and materials
Cost plus fixed fee
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The sponsor makes it clear that he does not want any of the team members to be overworked while working on a project. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?
Lag
Resource leveling
Resource smoothing
Free float
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A large development company has just initiated a project to build a 60-story building. The project will take approximately 3 years to complete with a cost of $550 million. The development company has started to facilitate funding for the project by asking private equity firms and banks. What tools does this best represent?
Financing
Funding limit reconciliation
Analogous estimates
Parametric estimates
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager, Mark, overheard that the project team is not satisfied with the way the budget was created. They strongly believe the project will be over budget at the end. What is the next best step for Mark?
Do nothing, because the team didn't speak to Mark about it
Review how the budget was created
Bring the team together and attempt to understand why they feel this way
Ask the sponsor for approval to increase the budget
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager has been informed that the company's senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?
Gantt chart
Milestone chart
WBS
Network diagram
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is currently working with the team to complete the office redesign project when a sponsor tells him to finish it 2 weeks sooner than planned. The project manager will need 4 new people to join the team to complete the work by the new deadline. What technique is best described in this scenario?
Critical path method
Schedule variance
Fast tracking
Crashing
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?