1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?

Weighing system

Screening system

Inspection and audits

Independent estimate

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager and team have decided to hire a contractor to complete building out the remaining section of the datacenter. They have the requirements listed in detail and would like to use a contract that would present the smallest amount of risk to the project. The project team members would like to purchase the materials themselves since there are very familiar with the work. What contract is best for this project?

Cost plus contractor fee

Cost plus project fee

Time and materials

Cost plus fixed fee

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The sponsor makes it clear that he does not want any of the team members to be overworked while working on a project. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?

Lag

Resource leveling

Resource smoothing

Free float

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A large development company has just initiated a project to build a 60-story building. The project will take approximately 3 years to complete with a cost of $550 million. The development company has started to facilitate funding for the project by asking private equity firms and banks. What tools does this best represent?

Financing

Funding limit reconciliation

Analogous estimates

Parametric estimates

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager, Mark, overheard that the project team is not satisfied with the way the budget was created. They strongly believe the project will be over budget at the end. What is the next best step for Mark?

Do nothing, because the team didn't speak to Mark about it

Review how the budget was created

Bring the team together and attempt to understand why they feel this way

Ask the sponsor for approval to increase the budget

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager has been informed that the company's senior management would like a meeting about the status of the project. What should the project manager take to display the current schedule of the project?

Gantt chart

Milestone chart

WBS

Network diagram

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is currently working with the team to complete the office redesign project when a sponsor tells him to finish it 2 weeks sooner than planned. The project manager will need 4 new people to join the team to complete the work by the new deadline. What technique is best described in this scenario?

Critical path method

Schedule variance

Fast tracking

Crashing

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?