Which of the following would be most appropriate when reviewing the number of changes to a project plan?
Identifying how many developers joined the project
Calculating total project expenditure
Comparing initial and final versions of the Gantt chart
Conducting a usability test of the completed software
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project experienced 11 changes to task durations, mostly during the testing phase. What is the most likely conclusion?
The development team lacked experience in user interface design
Testing was underestimated during initial planning
The SRS was not signed off by stakeholders
The hardware requirements were unclear
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following reasons for changes in a project plan is most likely considered unavoidable?
Late stakeholder request to redesign the interface
Developer requests to switch programming languages
API integration fails due to third-party platform removal
Client dissatisfaction with user manual layout
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Why is it important to record the reasons for changes to a project plan?
To reduce the amount of testing required
To help evaluate whether planning errors or external factors were involved
To increase the number of project meetings
To avoid documenting lessons learned
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which tool would be most appropriate for tracking and justifying changes made to a project plan?
Entity-relationship diagram
System flowchart
Project journal or version control log
Data dictionary
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A milestone was delayed by four days due to a developer being unavailable. Which category does this reason fall under?
Scope creep
Personnel issue
Technical problem
Data loss
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The addition of a new report generation feature halfway through development best reflects:
A. A miscalculation of estimated task durations
B. A personnel issue affecting critical tasks
C. Scope change initiated by stakeholders
D. A testing error in the evaluation stage
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?