1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A fillet welded patch must overlap sound base metal by:
at least 1”
at least 2”
the greater or 2T or 2”
the greater of 2T of 4”
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A fillet-welded patch covering a corroded area:
should extend into sound metal by 3”.
must be the same thickness as the equipment wall.
should be of the same or similar material as the equipment wall.
in alloy service must be the same material as the equipment wall.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The minimum thickness of a fillet-welded patch is:
the thickness of the equipment wall loss.
the nominal thickness of the equipment wall.
twice the nominal thickness of the equipment wall.
based on the calculated needed size of the attachment welds.
4.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
A fillet welded patch is installed on a 10’ diameter vessel. The vessel wall thickness is 0.750”.
Per PCC-2, how far must this patch be from an existing fillet welded patch?
12.4"
18.7"
13.4"
6.5"
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When grinding out a flaw, uneven and rough finishes could result in a failure by:
fatigue
erosion
temper embrittlement
galvanic corrosion
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A flaw is removed by grinding on a carbon steel material. This grinding wheel should:
not be used again.
examined with PT for cracking.
only be used in the future on the same materials (ASTM no. & grade).
not be used on austenitic stainless materials.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A small crack is going to be removed by grinding. Which of the following is correct?
The excavated area must be repaired with weld-buildup.
When performing weld buildup in this area, the GTAW process must be used.
If weld buildup is not used, the edges of the excavated area must have a 3:1 taper.
Small crack must be repaired with weld build up
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?