
PERT Pretest
Authored by Ney Froilan
Engineering
University
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
Graph or bar chart with a bar for each project activity that shows passage of time which provides visual display of project schedule
PERT/CPM
GANTT CHART
PRIMAVERA
BAR SCHEDULE
2.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
Indicates only precedence relationships and does not require any time of effort
Dummy
Slacks
Float
Event
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Latest time an activity can be completed without delaying critical path time
Early Start
Early Finish
Late Start
Late Finish
4.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
It refers to the amount of extra time that exists for an activity when all activities preceding it start at their Early Start (ES) date.
Float
Slacks
Total Float
Free Float
5.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
The longest path (time) in a network diagram and it determines the project duration.
Critical Activities
Critical Path
Activity on Node
Activity on Arrow
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A perimeter fence required 11,200 units of 6” CHB to complete. If a mason has an average daily installation productivity of 320 units, what is its estimated duration for a crew of 5 mason/day
6 days
7 days
3 days
4 days
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Draw the Network diagram given the ff:
A, B and C are starting activities and may begin at the same time.
D and E follows A and E is an ending activity
G follows and depends on C.
F is dependent on the completion of B and D.
G and F must be done before H, an ending activity, can start.
What is the Critical Path?
A=5, B=4, C=5, D=3, E=8, F=2, G=6 and H = 5 (all in days)
A-E
A-D-F-H
B-F=H
C-G-H
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?