Professional Solar Energy Installations training Examination

Professional Solar Energy Installations training Examination

University

60 Qs

quiz-placeholder

Similar activities

MPE I - Unit 3

MPE I - Unit 3

University

63 Qs

Structure C

Structure C

University

60 Qs

PRELIM EXAM - TECHNO_1

PRELIM EXAM - TECHNO_1

University

60 Qs

Introductory Activity: Measurement and Inspection

Introductory Activity: Measurement and Inspection

University

56 Qs

DM - Unit 1 - Intro to Design

DM - Unit 1 - Intro to Design

8th Grade - University

57 Qs

SEMANA 02 ADMINISTRACION DE OPERACIONES

SEMANA 02 ADMINISTRACION DE OPERACIONES

University

57 Qs

LEAN SIX SIGMA

LEAN SIX SIGMA

University

56 Qs

Introduction to CSS Quiz

Introduction to CSS Quiz

University

60 Qs

Professional Solar Energy Installations training Examination

Professional Solar Energy Installations training Examination

Assessment

Quiz

Engineering

University

Hard

Created by

Anonymous Anonymous

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

60 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A PV module has Pmax 288 W, Voc 40.0 V, Isc 9.5 A. At STC when loaded, Vmp = 32 V and Imp = 9.0 A. You must design an array of 6 modules in series and 4 strings in parallel. What is the expected system kWp, array voltage, and current at STC?

5.76 kWp, 240 V, 38 A

5.76 kWp, 240 V, 38 A

6.912 kWp, 192 V, 9 A

6.912 kWp, 192 V, 36 A

7.0 kWp, 192 V, 36 A

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

For a grid‑tied system, the designer needs 40 kWh/day with average irradiance 5 peak sun hours and must account for 25% total losses. What PV array STC power is required?

13.333 kW

8 kW

9.411 kW

133.33 kW

10.667 kW

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A rooftop 5 kW STC system has a performance ratio (PR) of 0.78. If the annual reference insolation is 1500 kWh/kWp, estimate the annual energy yield.

585 kWh

7500 kWh

5850 kWh

6750 kWh

7.5 kWh

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A system uses microinverters per module. Shading reduces a single module to 50% of its MPP. Compared with a string inverter under the same shading, what happens to system performance?

Microinverters suffer more loss.

Microinverters limit the loss to that module only; a string inverter sees the whole string loss.

Both systems are identical.

Microinverters cut the whole system to 50%.

None of the above.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A PV array with Voc per module = 48 V is connected 10 in series, with 8 strings in parallel. The maximum possible string Isc at STC is 9.0 A. What is the maximum short‑circuit current that the combiner fuse must handle instantaneously (nearest value)?

72 A

90 A

9 A

72 mA

8 A

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When designing a utility‑scale PV array for minimal degradation over time, which module characteristic should most influence orientation, stringing, and shading mitigation decisions?

Nameplate STC efficiency

Low‑light performance

Temperature coefficient of power and voltage

Aesthetics of module frames

Manufacturer warranty length

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A mini‑grid with 30 kWh daily load requires 2 days of autonomy. If allowable depth of discharge (DoD) is 80%, estimate the total battery bank capacity at 48 V (approximate).

1300 Ah

1560 Ah

900 Ah

800 Ah

2000 Ah

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?