Critical Path Analysis and Task Management
Interactive Video
•
Mathematics, Computers, Business
•
9th - 12th Grade
•
Practice Problem
•
Hard
Jackson Turner
FREE Resource
Read more
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the critical time in the context of the critical path algorithm?
The shortest sequence of tasks in the diagraph
The longest sequence of tasks in the diagraph
The average time of all tasks in the diagraph
The time taken by the first task in the diagraph
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the first step in the critical path algorithm?
Find the critical path in the diagraph
Find the shortest path in the diagraph
Add the last task to the priority list
Remove the first task from the diagraph
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is the first task in the priority list determined?
By selecting the task with the longest time
By selecting the task with the shortest time
By selecting the first task in the critical path
By selecting the last task in the critical path
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which path is considered the critical path?
The path with the most tasks
The path with the least tasks
The path with the shortest time
The path with the longest time
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the critical time for the path from task two to task seven?
16 hours
20 hours
22 hours
25 hours
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What happens after a task is added to the priority list?
The task is highlighted in the diagraph
The task is moved to the end of the diagraph
The task is removed from the diagraph
The task is duplicated in the diagraph
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After removing task two, which task is next in the priority list?
Task three
Task five
Task one
Task four
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?