The video tutorial covers the process of acquiring resources for a project, including obtaining team members, facilities, and equipment. It discusses the inputs, tools, and techniques involved, such as negotiation and decision-making strategies. The importance of ethical conduct in resource management is highlighted, along with the outputs like resource assignments and change requests. The tutorial emphasizes the need for careful planning and adherence to project management plans to ensure successful resource acquisition.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary benefit of the resource acquisition process?

It ensures all team members are highly skilled.

It eliminates the need for external resources.

It reduces project costs.

It outlines and guides resource selection and assignment.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document provides guidance on acquiring resources for a project?

Stakeholder Register

Resource Management Plan

Project Charter

Project Schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key factor that can influence the resource acquisition process?

Enterprise environmental factors

Project deadlines

Team member preferences

Client feedback

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which technique is commonly used in the resource acquisition process?

Brainstorming

Root cause analysis

Multicriteria decision analysis

SWOT analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a virtual team member?

A team member with the highest skill level

A team member who is not physically present with the team

A team member who is pre-assigned to the project

A team member who works on multiple projects simultaneously

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is an important output of the resource acquisition process?

Quality Control Reports

Risk Management Plan

Resource Calendars

Project Charter

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be done if a change is needed in the project management plan?

Submit a change request

Notify the project sponsor

Update the project charter

Directly implement the change