PMP Certification Training - Control Schedule

PMP Certification Training - Control Schedule

Assessment

Interactive Video

Information Technology (IT), Architecture, Life Skills

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers the control schedule process in project management, focusing on monitoring and updating project schedules. It discusses inputs like project management plans and organizational assets, tools and techniques such as data analysis and resource optimization, and outputs including schedule forecasts and change requests. The tutorial emphasizes the importance of managing schedule variances and maintaining baseline integrity.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the control schedule process?

To finalize project deliverables

To monitor and manage changes to the project schedule

To create a new project schedule

To eliminate all project variances

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document helps in identifying acceptable variances for schedule performance?

Project Charter

Quality Management Plan

Risk Management Plan

Schedule Management Plan

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key technique used to evaluate schedule status along the critical path?

Scope Creep

Stakeholder Analysis

Resource Leveling

Variance Analysis

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which tool can be used to track planned versus actual dates in a project?

Communication Plan

Risk Register

Project Management Information Systems

Stakeholder Register

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of schedule compression techniques?

To increase project costs

To align project activities with the plan

To extend project timelines

To reduce project scope

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What can work performance information be used for in the control schedule process?

To predict future performance

To eliminate all risks

To finalize project scope

To hide schedule variances

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be included in the schedule management plan to avoid misuse of performance data?

Stakeholder communication plan

Comprehensive risk analysis

Detailed cost estimates

Clear reporting expectations