PMP Certification Training - Create WBS

PMP Certification Training - Create WBS

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the Work Breakdown Structure (WBS) as a method to organize project scope by breaking down deliverables into manageable components. It covers the inputs, tools, techniques, and outputs of the WBS process, emphasizing the importance of expert judgment and decomposition. The tutorial also details the scope baseline and WBS dictionary, highlighting their roles in project management and communication.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a Work Breakdown Structure (WBS) in project management?

To organize project scope into manageable components

To allocate resources to project tasks

To provide a detailed schedule of project activities

To define the project budget

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a key input for creating a WBS?

Project budget

Requirements documentation

Scope management plan

Scope statement

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What technique is used to divide and subdivide project deliverables into smaller parts?

Decomposition

Resource leveling

Risk analysis

Critical path method

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the lowest level of a WBS called?

Project phase

Work package

Task list

Milestone

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document provides detailed information about each component in the WBS?

Risk register

Project charter

WBS dictionary

Stakeholder analysis