Microsoft Project 2021 From Beginners to Advanced - View Task and Deadlines

Microsoft Project 2021 From Beginners to Advanced - View Task and Deadlines

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to effectively view and manage tasks and their predecessors in a project management tool. It covers inserting the predecessors column, adjusting the timescale for better task visibility, highlighting task predecessors using the Gantt chart, customizing task layout, and enhancing readability with grid lines. These techniques help in organizing and understanding task dependencies and timelines more efficiently.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the predecessors column in the task entry table?

To display the start and end dates of tasks

To show which tasks are linked and their lead or lag times

To list all team members assigned to a task

To calculate the total project cost

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you change the timescale in a Gantt chart to view tasks more effectively?

By increasing the font size

By adjusting the project start date

By adding more tasks to the chart

By changing the display from days to weeks

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Task Path feature in the Gantt chart format tab do?

It highlights the tasks that are completed

It shows the tasks that are overdue

It highlights the predecessors that directly affect the selected task

It displays the total duration of the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which option is NOT a way to format task links in a Gantt chart?

Removing arrows between bars

Displaying task numbers only

Changing the color of task bars

Linking tasks with arrows

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can grid lines improve the readability of a Gantt chart?

By making the chart colorful

By adding more tasks to the chart

By increasing the size of the task bars

By helping to align tasks with their entries in the task table