PMP Certification Training - Identify Stakeholders

PMP Certification Training - Identify Stakeholders

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the process of identifying project stakeholders, emphasizing the importance of understanding their influence and interest for project success. It covers methods for finding stakeholders, including using project charters and business cases, and discusses tools and techniques for stakeholder analysis. The tutorial also explains how to classify stakeholders based on power and interest, and outlines the outputs of the stakeholder identification process, such as the stakeholder register and potential change requests.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it crucial to identify stakeholders early in a project?

To ensure their interests are incorporated from the start

To increase the project budget

To avoid any communication with them

To delay project timelines

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is a good starting point for identifying stakeholders?

Stakeholder Register

Project Charter

Risk Register

Issue Log

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the nature of stakeholder identification in a project?

It is a one-time process

It is an iterative process

It is only done at the end of the project

It is optional

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is stakeholder mapping used for?

To develop a risk management plan

To allocate project resources

To create a project timeline

To categorize stakeholders based on power and interest

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which stakeholders should be closely managed due to their high power and high interest?

Low power, low interest stakeholders

High power, high interest stakeholders

High power, low interest stakeholders

Low power, high interest stakeholders

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main output of the stakeholder identification process?

Issue Log

Project Charter

Stakeholder Register

Risk Management Plan

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does the stakeholder register assist in project management?

By outlining project timelines

By listing project resources

By detailing project risks

By organizing stakeholder information for effective communication