Microsoft Project 2021 From Beginners to Advanced - Reorganize the Structure

Microsoft Project 2021 From Beginners to Advanced - Reorganize the Structure

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to reorganize project tasks using indent and outdent features, and how to move tasks efficiently using cut and paste. It also covers the significance of blue shading as an indicator of recent changes in the task schedule.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary function of the indent and outdent buttons in a project schedule?

To assign resources to tasks

To adjust the hierarchy of tasks

To change task durations

To delete tasks

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method is considered more efficient for moving tasks in a long list?

Using the undo button

Re-entering tasks manually

Using cut and paste

Dragging and dropping

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens when you cut a summary task with its subtasks?

Only the summary task is removed

All tasks are deleted permanently

The tasks are removed from their current position

The tasks are duplicated

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you paste tasks after cutting them in a project schedule?

By re-typing them

By dragging them back

By pressing Control V or using the paste button

By using the delete button

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the blue shading in a project schedule indicate?

Tasks that are overdue

Tasks that have been recently modified

Tasks that are completed

Tasks that are on hold