Microsoft Project 2021 From Beginners to Advanced - Create an Auto-Scheduled Task

Microsoft Project 2021 From Beginners to Advanced - Create an Auto-Scheduled Task

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to create and manage auto scheduled tasks in a project management tool. It covers adding tasks to the entry table, setting task durations, and the impact of different time units like days and weeks. The tutorial also demonstrates how to link tasks using predecessors, ensuring that tasks follow a logical sequence. The planning wizard feature is introduced, which helps in linking tasks and managing start and finish dates automatically.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in adding an auto-scheduled task to the entry table?

Adjusting the timeline bar

Setting the finish date

Typing the task name in the first row

Clicking in the task mode column

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you specify a task duration in weeks instead of days?

Click the timeline bar

Type 'W' after the number

Use the up and down arrows

Type 'D' after the number

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if you enter '10' after changing the duration unit to weeks?

The task duration is set to 10 days

The task is removed from the schedule

The task duration is set to 10 weeks

The task duration remains unchanged

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Planning Wizard suggest when you enter a start date close to a task's finish date?

To delete the task

To link the tasks

To change the project start date

To ignore the date conflict

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a '1' in the predecessors column indicate?

The task is the first in the project

The task has no dependencies

Task #1 is a predecessor of the current task

The task is manually scheduled