Microsoft Project 2021 From Beginners to Advanced - Tracking and Managing Progress: Part 2

Microsoft Project 2021 From Beginners to Advanced - Tracking and Managing Progress: Part 2

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to set a status date for a project, which is crucial for tracking progress and performing earned value calculations. It demonstrates marking tasks as on track when they align with the status date and updating task details such as percentage complete, start and finish dates, and actual duration. The tutorial also covers handling incomplete tasks and making decisions when task progress does not fit within the status date period.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of setting a status date in project management?

To finalize the project budget

To assign tasks to team members

To calculate progress and earned value

To determine the project's start date

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens when you mark tasks as 'on track'?

The tasks are marked as incomplete

The actual start, finish, and duration are updated

The tasks are moved to a different project

The tasks are deleted from the schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does marking a task as 'on track' affect its baseline?

The baseline is shortened

The baseline remains the same as the actuals

The baseline is extended

The baseline is deleted

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What additional information can be updated for a task?

Percentage complete and actual duration

Project start date

Project budget

Team member assignments

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should you do if the period between actuals and the status date is insufficient?

Restart the project

Delete the task

Move actuals back in time or leave progress after the status date

Ignore the discrepancy