The video tutorial discusses a project managed by Alex with a $5 million budget and a 24-month timeline. It covers the use of three-point estimation for effort and cost, and addresses stakeholder concerns about project completion confidence. Alex is advised to perform quantitative risk analysis, using standard deviation to provide confidence levels. The tutorial also suggests using Monte Carlo simulation for predicting project outcomes and determining additional contingencies.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the budget allocated to Alex for the project?

$3 million

$7 million

$5 million

$10 million

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What technique did the team use for effort and cost estimation?

Critical Path Method

Three-point Estimation

Monte Carlo Simulation

PERT Analysis

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should Alex do to provide meaningful information to stakeholders about project completion confidence?

Perform qualitative risk analysis

Increase the project budget

Perform quantitative risk analysis

Extend the project timeline

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What confidence level is associated with ± 2 standard deviations?

68.3%

99.9999%

95.5%

99.73%

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What simulation method can be used to predict the probability of project completion within budget and schedule?

SWOT Analysis

Gantt Chart Analysis

Monte Carlo Simulation

PERT Analysis