Finding the Critical Path through a Network Analysis Diagram

Finding the Critical Path through a Network Analysis Diagram

Assessment

Interactive Video

Business, Social Studies, Physics, Science

University

Hard

Created by

Quizizz Content

FREE Resource

This video tutorial explains how to find the critical path in a network analysis diagram. It covers identifying critical activities by examining nodes with the same earliest start and latest finish times. The tutorial also discusses the concept of float time, which indicates spare time available for activities. The critical path is determined by the longest path through nodes with no float time, ensuring timely project completion.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of activity nodes having the same earliest start and latest finish times?

They help in resource allocation.

They indicate non-critical activities.

They identify critical activities for project completion.

They are used to calculate project costs.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activity is identified as critical between activity node one and two?

Acquiring materials

Assembling the product

Strategy meeting

Packaging design

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical activity between activity node two and three?

Packaging design

Strategy meeting

Acquiring materials

Assembling the product

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does float time represent in project management?

The total project duration

The spare time available for an activity

The cost of delaying an activity

The number of resources required

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is the strategy meeting not part of the critical path?

It is the most expensive activity.

It can be delayed without affecting the project deadline.

It is the shortest activity.

It requires the most resources.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is float time calculated?

By multiplying the duration by the number of resources

By subtracting the duration from the latest finish time and then subtracting the earliest start time

By adding the earliest start time and latest finish time

By dividing the total project time by the number of activities

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activities are identified as having zero float time?

Strategy meeting, acquiring materials, assembling the product

Packaging design, acquiring materials, assembling the product

Packaging design, strategy meeting, acquiring materials

Assembling the product, strategy meeting, packaging design