PMP Certification Training - Collect Requirements

Interactive Video
•
Information Technology (IT), Architecture
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary input to consider when collecting project requirements?
Stakeholder Register
Project Charter
Business Case
Lessons Learned Register
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a technique used for collecting requirements?
Focus Groups
Brainstorming
Document Analysis
Prototyping
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of using an affinity diagram in the requirements collection process?
To document stakeholder feedback
To group ideas into categories with similar themes
To prioritize project tasks
To create a visual model of the end product
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a context diagram, what term is used to describe people providing inputs or receiving outputs?
Participants
Actors
Stakeholders
Contributors
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main benefit of using prototypes in the requirements collection process?
They provide a detailed project schedule
They ensure all requirements are quantifiable
They allow stakeholders to visualize and modify requirements early
They document the project's high-level objectives
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the purpose of the requirements traceability matrix?
To link requirements to project deliverables and objectives
To create a visual model of the end product
To document all project assumptions
To prioritize project tasks
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which attribute is NOT typically included in a requirements traceability matrix?
Project Budget
Owner
Unique Identifier
Current Status
Similar Resources on Wayground
8 questions
What is a Requirements Traceability Matrix? And How to Create One.

Interactive video
•
12th Grade - University
2 questions
What is a Requirements Traceability Matrix? And How to Create One.

Interactive video
•
12th Grade - University
8 questions
PMP Certification Training - Perform Integrated Change Control

Interactive video
•
University
6 questions
PMP Certification Training - Summary - Project Communication Management

Interactive video
•
University
2 questions
PMP Certification Training - Plan Stakeholder Engagement

Interactive video
•
University
5 questions
PMP Certification Training - Plan Communicate Management

Interactive video
•
University
8 questions
PMP Certification Training - Collect Requirements

Interactive video
•
University
2 questions
PMP Certification Training - Collect Requirements

Interactive video
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade