Planning and Control Using Microsoft Project 365 and 2021 - Workshop 09 - Constraints

Planning and Control Using Microsoft Project 365 and 2021 - Workshop 09 - Constraints

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers project scheduling, focusing on setting constraints and managing negative float using a Gantt chart. It explains how to set bid submission constraints and adjust start dates for better supplier pricing. The tutorial also outlines five methods to bring a project back on time, such as shortening activity durations and adjusting calendars. Finally, it demonstrates reviewing and adjusting a bid document to manage project timelines effectively.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of setting a 'finish no later than' constraint in a project schedule?

To prevent a task from starting before a certain date

To ensure a task starts on a specific date

To guarantee a task is completed by a specific deadline

To allow flexibility in task completion

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does starting supplier quotes after Christmas affect the project timeline?

It accelerates the project completion

It extends the project end date by two days

It shortens the project duration

It has no impact on the project timeline

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a method to bring a project back on schedule?

Shortening activity durations

Adding more work time

Increasing project scope

Adjusting activity relationships

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the effect of reviewing the bid document in two days on the project schedule?

It creates a new critical path

It eliminates all negative float

It delays the project by a week

It has no effect on the critical path

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if there is a delay in any activity on the critical path?

The project gains additional float

The project scope is automatically reduced

The project end date remains unchanged

The project end date is immediately delayed