Why is qualitative risk analysis performed before quantitative risk analysis?
PMI-RMP Certification Training - Critical Success Factor and Project Risk Ranking

Interactive Video
•
Information Technology (IT), Architecture, Business
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
It requires more resources and time.
It is only used for low-priority risks.
It provides a detailed numerical analysis.
It is more subjective and less resource-intensive.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a critical factor in selecting a project model for quantitative risk analysis?
The model should focus only on cost.
The model should be the simplest available.
The model should mirror expected results.
The model should be the most complex available.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How can bias be reduced when gathering risk data?
By focusing only on quantitative data.
By ignoring qualitative data.
By involving multiple people in the assessment.
By using only one expert's judgment.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the project risk ranking allow for?
It allows for the exclusion of high risks.
It allows for the elimination of all risks.
It allows for comparisons among different projects.
It allows for the prioritization of low risks.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the probability and impact matrix display?
The number of risks and their probability and impact.
The number of risks and their cost.
The number of risks and their schedule.
The number of risks and their exposure.
Similar Resources on Quizizz
6 questions
PMI-RMP Certification Training - Case Study 3

Interactive video
•
University
2 questions
PMI-RMP Certification Training - Plan Risk Responses – Input, Tools and Techniques, and Output

Interactive video
•
University
6 questions
Risk Management 101 for IT Professionals Essential Concepts - Qualitative Risk Assessments

Interactive video
•
University
2 questions
PMI-RMP Certification Training - Perform Qualitative Risk Analysis Process

Interactive video
•
University
2 questions
CompTIA Security+ Certification SY0-601: The Total Course - Qualitative Risk Assessments

Interactive video
•
University
2 questions
PMI-RMP Certification Training - Stakeholder Participation, Risk Register Details, and Risk Description

Interactive video
•
University
6 questions
PMP Certification Training - Learning Objective - Project Risk Management

Interactive video
•
University
3 questions
PMP Certification Training - Summary - Project Risk Management

Interactive video
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade