Gullfaks to Hebron: Constructing Troll A

Gullfaks to Hebron: Constructing Troll A

Assessment

Interactive Video

Engineering, Arts, Architecture, Other

10th - 12th Grade

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers the construction and deployment of the Troll A platform, a massive natural gas extraction structure in Norway. It details the design considerations, construction techniques like slip forming, and the logistical challenges of assembling and positioning the platform in deep water. Safety measures, including ballast systems and weather planning, are also discussed to ensure successful operations.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What was the primary reason for choosing the name 'Troll' for the platform?

It reflects the platform's ability to withstand harsh conditions.

It was named after a famous Norwegian explorer.

It was the name of the company founder.

It was inspired by a local legend.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of using slip forming technology in construction?

It reduces the need for skilled labor.

It allows for construction in any weather condition.

It speeds up the construction process and improves quality.

It is more cost-effective than traditional methods.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why was the Troll A platform designed with a long and narrow deck?

To keep living quarters away from the working area for safety.

To reduce construction costs.

To allow for more storage space.

To improve the platform's stability.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What was the purpose of the heavy lift operation in the Troll A project?

To transport the platform to its final location.

To install the drilling equipment.

To mate the concrete support with the deck.

To test the platform's stability.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do meteorologists contribute to the towing operations of the platform?

By predicting the best time for construction.

By ensuring the platform is built to withstand storms.

By providing weather forecasts to avoid unforeseen conditions.

By helping design the platform's structure.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of ballast pumps during the platform's construction?

To adjust the platform's buoyancy during operations.

To provide power to the construction equipment.

To maintain the platform's temperature.

To supply water for concrete mixing.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is the refloating and towing of the platform usually done during the summer?

To avoid interference with marine wildlife.

To align with the company's financial calendar.

To ensure the weather is more predictable and calm.

To take advantage of longer daylight hours.