What is the primary purpose of Earned Value Management in project management?
PMP Certification Training - Project Cost Management

Interactive Video
•
Information Technology (IT), Architecture, Business
•
University
•
Hard
Quizizz Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To assess work progress against a baseline plan
To increase project costs
To delay project timelines
To eliminate project risks
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does the Earned Schedule enhance project schedule performance evaluation?
By reducing project scope
By transforming EVM metrics into time metrics
By increasing project costs
By eliminating project risks
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the Schedule Performance Index indicate?
The cost of the project
The quality of the project
How close the project is to being completed compared to the schedule
The number of team members
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is the expected finish date of a project calculated?
By adding the plan duration to the Schedule Performance Index
By dividing the plan duration by the Schedule Performance Index
By multiplying the plan duration by the Schedule Performance Index
By subtracting the Schedule Performance Index from the plan duration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a key consideration when tailoring project management processes?
Developing a list of questions to fit the unique project
Ignoring organizational policies
Using a one-size-fits-all approach
Focusing only on cost reduction
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does agile project management differ from traditional methods in estimating work effort?
Agile estimates work effort only at the end of the project
Agile does not estimate work effort
Agile uses a top-down approach
Agile uses a bottom-up approach
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In agile projects, what is often necessary for high variability projects?
Reducing team size
Frequent cost adjustments
Eliminating project scope
Increasing project duration
Similar Resources on Quizizz
6 questions
PMP Certification Training - Learning Objective - Project Communication Management

Interactive video
•
University
6 questions
Southern Co. CEO Expects Natural Gas, Renewables to Be Dominant for Years

Interactive video
•
University
6 questions
PMP Certification Training - PMI Certifications

Interactive video
•
University
6 questions
Agile Project Management - How to Use the Sprint Burndown

Interactive video
•
University
8 questions
What is the Agile Triangle - Value, Quality, and Constraints

Interactive video
•
12th Grade - University
8 questions
PMP Certification Training - Control Schedule

Interactive video
•
University
8 questions
What is PRINCE2 Agile? ...and Does it Make Sense?

Interactive video
•
12th Grade - University
6 questions
PMP Certification Training - Project Risk Management

Interactive video
•
University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade