What is a Critical Chain? Project Management in Under 5

What is a Critical Chain? Project Management in Under 5

Assessment

Interactive Video

Business

12th Grade - University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial introduces the concept of the critical chain, first proposed by Eliahu Goldratt, and its application in project management. It explains the use of different types of buffers—project, feeder, and resource buffers—to manage constraints and ensure timely project delivery. The tutorial also provides a practical approach to task estimation and scheduling, emphasizing the importance of contingency planning and the critical chain method for effective project management.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who first introduced the concept of the critical chain in project management?

Frederick Taylor

Peter Drucker

Eliahu Goldratt

Henry Gantt

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary focus of the critical chain method in project management?

Stakeholder communication

Budget allocation

Task prioritization

Resource management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of buffer is used to provide contingency time to the entire project?

Feeder buffer

Time buffer

Resource buffer

Project buffer

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a feeder buffer in project management?

To improve team communication

To allocate budget effectively

To ensure non-critical paths deliver on time

To manage resource availability

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the example with Amit, Becky, and Chang, how many days of contingency did Chang request?

Five days

Two days

Three days

Four days

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of using a single block of contingency time in scheduling?

Improved stakeholder satisfaction

Reduced project costs

Enhanced flexibility against risks

Increased team motivation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does the critical chain approach help in delivering projects on schedule?

By reducing the project scope

By increasing the number of resources

By enhancing team collaboration

By applying buffers to manage risks