Microsoft Project 2021 From Beginners to Advanced - Example of Earned Value Analysis

Microsoft Project 2021 From Beginners to Advanced - Example of Earned Value Analysis

Assessment

Interactive Video

Information Technology (IT), Architecture, Social Studies

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers earned value analysis, focusing on setting and updating baselines, understanding percentage complete, and analyzing earned value reports. It explains the importance of comparing progress with a baseline and how to adjust baselines when project changes occur. The tutorial also discusses the difference between percentage complete and physical percentage complete, and how to interpret earned value reports to assess project performance.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of saving a baseline in earned value analysis?

To track the number of tasks completed

To compare project progress against a set standard

To ensure all resources are utilized

To calculate the total project cost

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should you consider saving a new baseline?

When a project is completed

When a major change occurs in the project

When a task is delayed by a day

When a new team member joins

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the difference between percentage complete and physical percentage complete?

Percentage complete is for resources, while physical percentage complete is for tasks

Percentage complete is automatic, while physical percentage complete requires manual input

Percentage complete is based on cost, while physical percentage complete is based on time

Percentage complete is calculated manually, while physical percentage complete is automatic

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method should you use if you want the project to calculate earned value automatically?

Physical percentage complete

Resource-based calculation

Manual calculation

Percentage complete

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a horizontal line in the earned value report charts indicate?

Budget constraints

Future values

Current project status

Past performance

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an earned value report, what does it mean if the grey and blue lines are above the orange line?

The project is ahead of schedule

The project is on track

The project is not performing well

The project is under budget

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a negative cost variance (COV) indicate in an earned value report?

The project is on track

The project is ahead of schedule

The project is over budget

The project is under budget