What is a PERT Chart? Project Management in Under 5

What is a PERT Chart? Project Management in Under 5

Assessment

Interactive Video

Other

9th - 10th Grade

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the PERT chart, a network chart methodology developed in the 1950s by the US Navy and Booz Allen Hamilton. It compares PERT with the critical path method, highlighting that PERT uses a three-point estimation for task durations, unlike the single-point estimate in the critical path method. The tutorial details how to calculate average durations and standard deviations using PERT, emphasizing the use of modern software for project estimation. It concludes by advocating for the broader use of PERT while cautioning against over-reliance on its estimates.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does PERT stand for?

Plan Evaluation and Review Technique

Process Evaluation and Review Technique

Project Estimation and Review Technique

Program Evaluation and Review Technique

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does the PERT method differ from the critical path method in terms of activity representation?

Both use activities on lines.

PERT uses activities on nodes, while critical path uses activities on lines.

PERT uses activities on lines, while critical path uses activities on nodes.

Both use activities on nodes.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of estimate does the critical path method use for activity duration?

Three-point estimate

Single-point estimate

Four-point estimate

Double-point estimate

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In PERT, which estimate is given the highest weighting when calculating the average duration?

Most likely estimate

Pessimistic estimate

Optimistic estimate

All estimates are equally weighted

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the standard deviation calculated in the PERT method?

Subtract the optimistic estimate from the pessimistic estimate and divide by 6

Subtract the most likely estimate from the optimistic estimate and divide by 6

Add all estimates and divide by 3

Add the optimistic and pessimistic estimates and divide by 2

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of using the PERT method in project management?

To create a visual representation of project tasks

To estimate project costs

To estimate project durations and manage uncertainties

To allocate resources efficiently

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What advantage does modern software provide when using the PERT method?

It replaces the need for project managers

It provides real-time project cost analysis

It automates the calculation of average durations and standard deviations

It eliminates the need for estimates