PMP Certification Training - Implement Risk Responses

PMP Certification Training - Implement Risk Responses

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the process of implementing risk responses in project management. It highlights the benefits of executing agreed-upon risk response plans to manage project risks effectively. The tutorial covers the inputs required, such as the risk management plan and project documents, and discusses the tools and techniques used, including expertise and project management systems. It also outlines the outputs, such as change requests and updates to project documents.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary benefit of implementing agreed upon risk response plans?

To increase project costs

To eliminate all project risks

To ensure risk responses are executed as planned

To delay project timelines

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is reviewed first when implementing risk responses?

Stakeholder register

Risk management plan

Project charter

Quality management plan

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What role do project management information systems play in implementing risk responses?

They eliminate the need for risk management

They ensure risk response plans are integrated with other project activities

They create new project risks

They replace the need for human expertise

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why might interpersonal and team skills be necessary in implementing risk responses?

To encourage risk owners to take necessary actions

To increase project costs

To eliminate the need for a risk management plan

To avoid project documentation

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What might be a result of implementing risk responses?

An increase in project risks

A reduction in project team size

A decrease in project scope

A change request to project baselines