Agile Masterclass: Agile for Project Management - Introduction to Estimation
Interactive Video
•
Business
•
9th - 10th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Read more
7 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of estimation in planning?
To provide an exact calculation
To make an educated guess
To avoid any guesswork
To ensure complete accuracy
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In traditional estimation, what is typically estimated?
Business values
Efforts required for tasks
Relative size of tasks
Complexity of user stories
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What unit is used in agile estimation to measure the complexity of a user story?
Days
Story points
Weeks
Hours
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How does agile estimation differ from traditional estimation in terms of focus?
Agile focuses on exact hours
Agile focuses on fixed scope
Agile focuses on relative size
Agile focuses on absolute time
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a key characteristic of agile estimation regarding plans and estimates?
They are revisited in every iteration
They are fixed once done
They are only revised at the end
They are never revised
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the hypothetical example, why is the kitchen estimated at eight points?
It is easy to paint
It is complex due to plumbing
It is the smallest room
It is the largest room
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which factor is NOT considered when estimating the size of a user story in agile?
Exact time
Risk
Complexity
Business value
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?