PMI-RMP Certification Training - Case Study 5

PMI-RMP Certification Training - Case Study 5

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video discusses a project activity initially estimated to take five days with two resources. During the project, the team discovers that purchasing a $100 software license could reduce the task to under two hours. The project manager should analyze this opportunity, evaluate the cost-benefit, and ensure the software is procured to save on resources and time.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many days and resources were initially estimated for the project activity?

Ten days with one resource

Two days with five resources

Five days with two resources

Three days with three resources

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What did the team realize about the project activity during its course?

It needed additional training for the team

It could not be completed within the estimated time

It required more resources than initially planned

It could be done in less than two hours with a software purchase

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the cost of the software license that could expedite the project activity?

$50

$150

$200

$100

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should the project manager do upon discovering the software solution?

Evaluate the cost-benefit of purchasing the software

Delay the project to find a better solution

Hire more resources to speed up the process

Ignore the software and stick to the original plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many man-days could potentially be saved by purchasing the software?

5 man-days

10 man-days

15 man-days

20 man-days