PMI-RMP Certification Training - Conducting Risk Audit

PMI-RMP Certification Training - Conducting Risk Audit

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers various aspects of risk management in project management, focusing on risk audits, trend analysis, variance analysis, reserve analysis, and status meetings. It explains how to conduct a risk audit for an ERP implementation, the importance of trend analysis in monitoring project performance, and how variance analysis helps in understanding deviations from the project plan. Reserve analysis is discussed in terms of contingency and management reserves, and the role of status meetings in managing risks is highlighted.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary role of an external consultant in a risk audit?

To conduct financial audits

To implement new risk management procedures

To familiarize with existing procedures and monitor risk assessment

To replace the internal risk management team

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of trend analysis in project management?

To create new project plans

To finalize project budgets

To hire new team members

To determine if project performance is improving or deteriorating

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does a control chart assist in project management?

By tracking team attendance

By calculating project costs

By scheduling team meetings

By monitoring project parameters and identifying risks early

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does variance analysis compare in a project?

The project goals with the company mission

The planned and actual risk impacts

The team size with project requirements

The project location with client preferences

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of technical performance measurements?

To assess if technical objectives are being met

To evaluate team communication skills

To finalize project deadlines

To determine project location

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are contingency reserves used for in a project?

To redesign project plans

To purchase new equipment

To serve as buffers for scheduled risks or setbacks

To hire additional staff

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why should risk discussions be included in status meetings?

To ensure risks are addressed before they become issues

To increase meeting duration

To reduce project costs

To finalize project deadlines