PMI-RMP Certification Training - Risk Breakup Structure, Effect, and Source-Based Risk Calculation

PMI-RMP Certification Training - Risk Breakup Structure, Effect, and Source-Based Risk Calculation

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial covers the concept of risk breakdown structure (RBS) in project management, explaining how it helps organize potential risk areas. It also discusses effect-based risk classification, focusing on managing uncertainties in time, cost, scope, and quality. The tutorial further explores source-based risk classification, analyzing risks based on their origin, whether internal or external to the project or organization.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a Risk Breakdown Structure (RBS) in project management?

To organize potential areas of risk

To create a detailed project schedule

To define project objectives

To allocate project resources

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a component of the project management triad?

Time

Stakeholder

Cost

Quality

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is managing uncertainty in time, cost, and scope crucial for project success?

It ensures stakeholder engagement

It guarantees project funding

It simplifies project documentation

It leads to effective risk management

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can risks be classified in source-based risk classification?

By their potential cost to the project

By their likelihood of occurrence

By their origin, such as internal or external

By their impact on project quality

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an example of an external risk source?

Project timeline

Market competition

Organizational culture

Project team skills