PMP Certification Training - Monitor and Control Project Work

PMP Certification Training - Monitor and Control Project Work

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the process of monitoring and controlling project work, highlighting the differences between monitoring and controlling. It covers the inputs, tools, techniques, and outputs involved in this process. Key inputs include the project management plan and various project documents. Tools and techniques such as expert judgment, data analysis, and trend analysis are discussed. The outputs include work performance reports and change requests. The tutorial emphasizes the importance of analyzing variances and making informed decisions to ensure project objectives are met.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of monitoring project work?

To create new project objectives

To track and report project progress

To finalize project deliverables

To initiate project closure

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document contains the project baselines and variance thresholds?

Lessons Learned Register

Risk Register

Project Management Plan

Quality Report

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of expert judgment in controlling project work?

To create new project plans

To analyze performance and address variances

To approve project deliverables

To finalize project budgets

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which analysis technique is used to forecast future performance based on past results?

Root Cause Analysis

Cost Benefit Analysis

Variance Analysis

Trend Analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of work performance reports?

To finalize project budgets

To create awareness and generate decisions

To approve project deliverables

To initiate new projects

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if a change request is initiated during the monitoring process?

It is ignored

It goes to the perform integrated change control process

It is automatically approved

It is sent to the project sponsor

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document is updated with effective responses for variances and corrective actions?

Quality Report

Lessons Learned Register

Project Management Plan

Risk Register