Planning and Control Using Microsoft Project 365 and 2021 - Workshop 16 - Assigning Resources to Tasks

Planning and Control Using Microsoft Project 365 and 2021 - Workshop 16 - Assigning Resources to Tasks

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Wayground Content

FREE Resource

The video tutorial covers the process of assigning resources to tasks in a project management setting. It begins with an introduction to resource assignment, followed by a demonstration of various methods to assign resources, including using the Gantt chart and entry table. The tutorial then explains how to assign multiple resources to multiple activities efficiently. Finally, it explores the use of Task and Resource Usage forms to analyze resource allocation, cash flow, and resource demand over time.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in assigning resources to tasks in a project?

Opening the Gantt chart

Viewing the resource sheet

Downloading the PDF

Assigning costs

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method allows you to assign multiple resources to multiple activities at once?

Using the task details form

Using the assign resources form

Double-clicking to open task information

Right-clicking and showing the split

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you adjust the time scale to view a daily cash flow in the Task Usage form?

Insert a cost column

Click minus a couple of times

Select all activities

Right-click and hide the work

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which form allows you to see the number of hours against each resource?

Task details form

Resource sheet

Gantt chart

Task Usage form

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Resource Usage profile primarily show?

Daily cash flow

Resources and their associated tasks

Tasks and their durations

Cost per resource

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens in the Resource Usage profile if a resource is overloaded?

The hours are reduced automatically

The resource name turns blue

The task is removed

The resource line turns red

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Resource Usage profile, what can you do to see only the resources assigned to a specific activity?

Select a single activity

Select all activities

Hide the work

Insert a cost column