The video tutorial explains cost accrual in project management, using a dummy project with tasks and resources. It covers different accrual methods, such as prorated, start, and end, and demonstrates how these affect project costs. The tutorial also shows how to assign resources and adjust cost settings, emphasizing the importance of understanding accrual methods for accurate cost management.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of understanding different cost accrual methods in project management?

To assign tasks to team members

To calculate the project's total duration

To recognize when costs are incurred

To determine the project's start date

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the dummy project setup, how many tasks and resources are initially defined?

7 tasks and 7 resources

10 tasks and 10 resources

5 tasks and 5 resources

3 tasks and 3 resources

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens to the actual cost of Task A when the project status is updated to the current date?

The actual cost decreases

The actual cost matches the fixed cost

The actual cost doubles

The actual cost remains at 0

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the cost for Task B distributed when using the prorated method?

It is not incurred at all

It is spread over the task's duration

It is incurred at the end

It is incurred at the start

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the effect of assigning resources to tasks in terms of project cost?

It decreases the total project cost

It only affects the project timeline

It has no effect on the project cost

It increases the total project cost

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which method is set as the default for fixed cost accrual in the project settings?

None

Prorated

End

Start

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the standard hourly rate for Resource two in the project?

$80.00

$70.00

$50.00

$60.00