Microsoft Project 2021 From Beginners to Advanced - Variable Material Costs

Microsoft Project 2021 From Beginners to Advanced - Variable Material Costs

Assessment

Interactive Video

Information Technology (IT), Architecture, Business, Engineering, Other

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to manage variable material costs in building projects, focusing on a task involving pouring concrete and using a pump. It covers setting up material resources like concrete, pump, and fuel, and assigning them to tasks. The tutorial also details cost calculations based on resource usage and task duration, providing a comprehensive view of managing project costs effectively.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key factor that affects the amount of material assigned to a task?

The location of the project

The duration of the task

The color of the material

The number of workers

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the building project example, what is the task called?

Footings

Foundation

Roofing

Framing

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the cost of concrete measured in the project?

Per square meter

Per cubic yard

Per ton

Per gallon

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the day rate for using the pump in the project?

$5.00

$10.00

$15.00

$20.00

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the cost per litre of fuel used in the project?

$1.00

$0.50

$1.50

$2.00

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many cubic yards of concrete are assigned to the task?

10 cubic yards

15 cubic yards

20 cubic yards

25 cubic yards

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the total cost for the project task as calculated?

$1600

$1694

$1500

$1700