Microsoft Project 2021 From Beginners to Advanced - The Critical Path

Microsoft Project 2021 From Beginners to Advanced - The Critical Path

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the concept of the critical path in project management, highlighting its importance as the longest sequence of tasks that can affect the project finish date. It demonstrates how to view critical tasks using a Gantt chart and discusses the concept of slack, which is the amount of time a task can be delayed without affecting the project. The tutorial also covers how to add a slack column to task tables and the impact of modifying task durations on the critical path. Finally, it shows how to filter and view only critical tasks.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in project management?

Tasks that have the most resources allocated

Tasks that can be delayed without affecting the project

The longest sequence of tasks in a project

The shortest sequence of tasks in a project

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why are tasks on the critical path important?

They are the least expensive tasks

Any delay in these tasks affects the project finish date

They have the most resources allocated

They can be completed in any order

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does slack or float represent in project management?

The number of resources required for a task

The total duration of the project

The cost of delaying a task

The amount of time a task can be delayed without affecting the project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens to a task on the critical path if its duration is increased?

It requires fewer resources

It delays the project finish date

It is removed from the critical path

It gains more slack

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you view only the critical tasks in a project?

By increasing the duration of all tasks

By filtering tasks using the critical filter

By allocating more resources to tasks

By using the Gantt chart format tab