Microsoft Project 2021 From Beginners to Advanced - Delay a Task

Microsoft Project 2021 From Beginners to Advanced - Delay a Task

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains how to manage resource over-allocation in project planning by using tasks 10 and 11 as examples. It highlights the importance of predecessors in organizing schedules and introduces the Leveling Gantt view for better task management. The concept of E days, which includes both working and non-working days, is explained. The tutorial demonstrates how to adjust task delays to manage resources effectively, ensuring tasks do not overlap unnecessarily.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main issue with tasks 10 and 11 in the project plan?

They are over-allocated to the same resource.

They are not assigned to any resource.

They have too many predecessors.

They are scheduled on non-working days.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to have predecessors for tasks?

To assign more resources to tasks.

To increase the duration of tasks.

To organize the schedule and manage resource allocation.

To ensure tasks are completed in parallel.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What additional information does the Leveling Gantt view provide?

Project milestones and deadlines.

Resource costs and budget allocation.

Task dependencies and critical path.

Leveling delay and task successors.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the 'E' in E days stand for?

Elapsed

Estimated

Exclusive

Extended

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why did task 11 still overlap with task 10 after setting a 10 E days delay?

The delay was not applied correctly.

Task 10 was extended unexpectedly.

E days include weekends, which were not accounted for.

Task 11 has a higher priority.