Microsoft Project 2021 From Beginners to Advanced - What are Resources?

Microsoft Project 2021 From Beginners to Advanced - What are Resources?

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the three types of resources in project management: work, material, and cost resources. It discusses how each type affects project timelines and costs. Work resources are managed by time and availability, material resources by quantity, and cost resources by task-specific expenses. The tutorial emphasizes understanding these resources to effectively plan and execute projects.

Read more

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can adding a second work resource to a task affect its duration?

It has no effect on the task duration.

It halves the duration of the task.

It triples the duration of the task.

It doubles the duration of the task.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key consideration when assigning work resources to tasks?

The resource's favorite food.

The color of the resource's uniform.

The resource's preferred working location.

The resource's availability and percentage of time they can work.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why are calendars important for work resources?

They are used to track holidays.

They determine the working hours and availability of resources.

They are used to plan vacations.

They help in scheduling meetings.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How are material resources assigned in a project?

By the number of hours worked.

By the number of days they are used.

By the quantity needed.

By the number of people using them.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What distinguishes cost resources from work and material resources?

They are always related to travel expenses.

They are only used in construction projects.

They are variable costs that can change from task to task.

They are always fixed costs.