What is the Critical Path Method (CPM)? PM in Under 5 minutes

What is the Critical Path Method (CPM)? PM in Under 5 minutes

Assessment

Interactive Video

Business, Information Technology (IT), Architecture

12th Grade - University

Hard

Created by

Wayground Content

FREE Resource

The video tutorial explains the critical path method, a project management technique developed in the 1950s. It compares this method with the PERT method, highlighting differences in representation and estimation. The tutorial outlines a six-step process to apply the critical path method, emphasizing its use in project planning and monitoring. It also discusses the concept of float and resource management, and compares the critical path method with Gantt charts, noting that both are different ways to represent the same project information.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who were the developers of the Critical Path Method?

Albert Einstein and Niels Bohr

Henry Gantt and Frederick Taylor

Booz Allen and the US Navy

Morgan Walker and James Kelly

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary difference in how PERT and CPM represent activities?

Both use nodes for activities

PERT uses arrows for activities, CPM uses nodes

PERT uses nodes for activities, CPM uses arrows

Both use arrows for activities

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many point estimates does the CPM use for activity durations?

A single point estimate

Two point estimates

Three point estimates

No estimates

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in applying the Critical Path Method?

Specify each activity

Draw the network diagram

Identify the critical path

Estimate activity durations

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'float' refer to in project management?

The number of resources available

The shortest path through the network

The ability to delay an activity without affecting the project completion

The total duration of the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a common alternative to the Critical Path Method for project managers?

Histogram

Flowchart

Gantt chart

PERT chart

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the relationship between a Gantt chart and a CPM network diagram?

They are two different representations of the same information

A Gantt chart is a type of CPM diagram

They are unrelated tools

A CPM diagram is a type of Gantt chart