Project Management Concepts and Calculations

Project Management Concepts and Calculations

Assessment

Interactive Video

Computers

9th - 10th Grade

Hard

Created by

Thomas White

FREE Resource

This video tutorial explains how to calculate the earliest start time, latest start time, and slack time using an activity graph with durations. It covers the importance of directed graphs in project management and provides a step-by-step guide to determining these times for various activities. The tutorial also explains how to calculate slack and identify the critical path, emphasizing the role of data structures and algorithms in these processes.

Read more

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the three main concepts discussed in this video?

Graph theory, data structures, and algorithms

Project management, resource allocation, and budgeting

Time management, scheduling, and deadlines

Earliest start time, latest start time, and slack time

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is understanding directed graphs important for this tutorial?

They help in understanding project budgets

They play a role in calculating start times and slack

They are essential for calculating project costs

They are used to determine team roles

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of a directed acyclic graph in this context?

It helps in determining project costs

It is used to calculate earliest and latest start times

It is essential for team management

It helps in resource allocation

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the earliest start time for activity A?

Day 2

Day 3

Day 1

Day 4

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the earliest start time for activity B determined?

By adding the duration of A to the start of the project

By subtracting the duration of A from the start of the project

By multiplying the duration of A by two

By dividing the duration of A by two

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the earliest start time for activity C?

Day 4

Day 6

Day 3

Day 5

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why does activity E have an earliest start time of 9 days?

Because it is the final activity

Because it has the longest duration

Because it depends on the completion of both C and D

Because it starts immediately after A

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?