WorksheetsEOT, LD and L&E
Total questions: 5
Worksheet time: 4mins
Between SIA, PSSCOC and REDAS, which one(s) requires the contractor to submit sufficient supporting information for the Architect/SO/ER to determine the EOT duration?
SIA
SIA & PSSCOC
SIA & REDAS
SIA, PSSCOC & REDAS
What is Liquidated Damages?
The amount of damages the Client can recover if the Contractor breaches the contract by not finishing the work on time.
Housing damages caused by rain or water-related events.
A bonus that the Client deserved if the Contractor breaches the contract by not finishing the work on time.
On which grounds can the Contractor claim for L&E?
Trump & Kim's summit takes place near the site, so no noisy works is allowed.
Termination of Sub-Contractor engaged by the Employer.
Malaysia's election day.
Accident caused by direct Sub-Contractor which resulted in stop work for investigation by MOM.
Main Contract LD: $ 50,000/day
Specific Work #1: $1,500/day
Specific Work #2: $500/day
What is the maximum LD amount for a day?
$52,000
Singapore Dollars Fifty Thousand Only
$51,500
Singapore Dollars Fifty Thousand and Five Hundred Only
Under which Form of Contract can the Contractor claim EOT for "The use or occupation of the Employer of any part of the Works"?
REDAS & PSSCOC
SIA & REDAS
PSSCOC, REDAS & SIA
PSSCOC