How many bubbles of life in a typical engineer as being shared in the class?
1
2
3
4
What is the correct sequence of a project life cycle?
Construction - Conceptual - Detailed Engineering & Procurement - FEED- Commissioning
Commissioning - Construction - Conceptual - Detailed Engineering & Procurement - FEED
FEED- Conceptual - Detailed Engineering & Procurement- Construction -Commissioning
Conceptual - FEED- Detailed Engineering & Procurement- Construction -Commissioning
What is the one of the common factors of HSE thoroughout the project life cycle?
Schedule
Risk
Budget
Resources
What is the correct sequence of the effectiveness of hierarchy control? From most to least
PPE-Administrative-Engineering-Isolation-Substitute-Eliminate
Substitute-PPE-Administrative-Engineering-Isolation- PPE
Eliminate-Substitute-Isolation-Engineering-Administrative-PPE
Engineering-PPE-Administrative-Isolation-Substitute- Eliminate
The earlier the project , the more reasonably practical are from the higher tier controls. True or False?
True
False
In a project execution, HSE is only confined to Safety Engineer. True or False?
True
False
What are some of the processes put in place to identify risks and mitigate them during a project execution?
HAZID
HAZOP
ENVID
All of the above
Who has the influence to make competent engineering judgement in the processes?
Everybody else but not me
Everybody including me
Vendors / Suppliers
My management
What is the main element to manage to ensure the safety impact is reduced to as low as reasonable practicable?
RISK
SCHEDULE
REPUTATION
COST
HSE is applicable both in the professional and personal level.
True or False?
True
False