Unit 102-Contribute to setting out and building of masonry structures up to damp proof course

Total questions: 20

Worksheet time: 20mins

Name
Class
Date
1.

What drawing would be used to show the foundation detail?

a)

Front elevation

b)

Location plan

c)

Site plan

d)

Section through.

2.

Which scale is commonly used on a detail drawing?

a)

1:5

b)

1:100

c)

1:250

d)

1:2500

3.

Which one of the following could be used to take a measurement from an original drawing?

a)

Protractor

b)

Scale rule

c)

T square

d)

Set square

4.

Why must existing gas supplies be located before building work begins?

a)

To cover them with concrete for protection

b)

To ensure new pipework can be connected

c)

To allow maintenance to be carried out

d)

To prevent damage to the services.

5.

Why should site clearance take place?

a)

To allow materials to be delivered

b)

To ensure the site is ready for setting out

c)

To reduce the cost of removing the topsoil

d)

To allow Building Inspectors time to inspect the site

6.

Which one of the following describes the building line?

a)

A line from which setting out will be taken, approved by the HSE

b)

The centre line of a proposed or existing building

c)

A gridline used to mark the position of internal walls

d)

A line from which setting out will be taken, approved by the Local Authority.

7.

What ratio should be used when setting out a right angled corner?

a)

1:2:3

b)

3:4:5

c)

4:5:6

d)

5:6:7

8.

Which one of the following should be used to set out a right angled quoin?

a)

Storey rod

b)

T square

c)

Straight edge

d)

Builder’s square

9.

It is important to check the diagonal measurements when setting out to ensure the building is;

a)

level

b)

plumb

c)

square

d)

gauged

10.

Which one of the following will detail the safe sequence of work?

a)

Method statement

b)

Building Regulations

c)

Specification

d)

Drawings

11.

What action should be taken if the material being used on site does not match the material stated in the specification?

a)

Report to the supervisor and ask for clarification

b)

Continue working with the current materials

c)

Report to the HSE and ask for clarification

d)

Seek approval from the Building Inspector

12.

When transferring levels over a distance, a spirit level should be used with a;

a)

builder’s square

b)

straight edge

c)

site square

d)

storey rod

13.

A site datum is used to establish a;

a)

levels

b)

lengths

c)

square

d)

position

14.

How should a wall position be transferred from profiles onto foundation concrete?

a)

Level from ranging line and mark using mortar screed

b)

Plumb from ranging line and mark using mortar screed

c)

Gauge from ranging line and mark using concrete screed

d)

Measure from ranging line and mark using concrete screed

15.

Why is it important to protect site datums from damage?

a)

To comply with HSE guidance

b)

To comply with Building Regulations

c)

To ensure the accuracy of levels taken

d)

To ensure the accuracy of dimensions taken

16.

What is the timber profile shown in the image used for?

a)

To provide access for excavators

b)

To support the sides of a trench

c)

To set out wall positions

d)

To set out levels

17.

Which one of the following should be used when checking for gauge?

a)

Ranging line

b)

Straight edge

c)

Tape measure

d)

Builder’s square

18.

A 90° angle should be established using a;

a)

ranging line

b)

straight edge

c)

profile board

d)

builder’s square

19.

When pouring concrete into foundation trenches, pegs can be used to ensure the correct ;

a)

level

b)

strength

c)

workability

d)

finish

20.

How can a spirit level be checked for accuracy?

a)

By using a builder’s square to check the level

b)

By reversing the level between two level pegs

c)

By cleaning the level after use

d)

By levelling against a storey rod