"How a process is performed to provide confidence that quality requirements are being met" is...
Quality Planning
Quality Improvement
Quality Control
Quality Assurance
The SCMU includes staff from which organization(s)?
Alberta Transportation
Mainroad
WSP
Mixture of all
How much of the lump sum is at risk?
$1M per month
A quarter of the monthly payment
20% of the entire lump sum
All of it
Which of these is not a criteria in the annual performance review?
Safety
Responsiveness
Innovation
Risk
In the context of the contract, what is a defect?
Completed work that has failed
Something contributing to a reduction in the specified level of service
A breach of the OPM requirement
Faults resulting in a non-compliance
When does the 'Maximum Time for Defect Repair' timing end?
When permanent repair of the defect is programmed
When the repair is completed
When someone has assessed the defect
When the defect is forgotten about
Which word best describes how Provisional Maintenance should be programmed?
Collaboratively
Autocratically
Democratically
Autonomously
After being provided a list of audit sections, how long do the SCMU have to complete audit inspections?
One week
One month
Ten days
48 Hours
How long is a typical audit section?
1 centreline kilometer
5 centreline kilometers
2 lane kilometers
10 lane kilometers
How many non-compliances will result in a payment adjustment?
Ten
It depends on the number and their severity
One
When at least half of the OPMs fail