Total questions: 10
Worksheet time: 5mins
1. Which type of points is not monitored by TNBD RTU MRMU ?
DI
DO
AI
CES
What are the minimum point of DI for RTU VCB?
52
60
8
7
Analog input ports support the following input options and ranges EXCEPT
± 1mA
±48mA
±0-20mA
±4-20mA
When is SAT done for RTU sites ?
Before installing the RTU
After installing the RTU
During installation of the RTU
No need to do SAT on the RTU
What are the minimum point of DBC?
7
8
52
12
What type of Cable for No. 2 ?
2 Core x 2.5mm2 armoured
10 pair x 1mm2 twisted armoured
3 Core x 2.5mm2 armoured
4 Core x 4.0mm2 armoured
What type of Cable for No. 3 ?
2 Core x 2.5mm2 armoured
10 pair x 1mm2 twisted armoured
3 Core x 2.5mm2 armoured
1 Core x 50mm2 non armoured
What type of Cable for No. 4 ?
2 Core x 2.5mm2 armoured
10 pair x 1mm2 twisted armoured
3 Core x 2.5mm2 armoured
1 Core x 50mm2 non armoured
What type of Cable for No. 5 ?
2 Core x 2.5mm2 armoured
10 pair x 1mm2 twisted armoured
Multi I/O 40 core @ 19-50 Core x 1mm2 armoured
1 Core x 50mm2 non armoured
What test is done between SIP/RCB & RTU ?
SAT
Local Commissioning
Integration Test
Full Commissioning