Font size
Worksheets15 - Critical Path Analysis & Gantt Charts
Total questions: 8
Worksheet time: 6mins
Identify the longest task?
Fill Kettle
Boil Kettle
Put tea in cup
Put sugar in cup
Get milk out of fridge
How many milestones are there?
(a)
How many tasks are dependent on pouring water into a cup?
(a)
How many seconds form the critical path?
(a)
What is Critical Path Analysis
A project management technique for process planning that defines critical (milestones) and non-critical tasks
A graphical display of project activities represented by an area of land showing physical features
A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site
A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project
What does PERT stand for?
Project Evaluation and Review Technique
Programme Estimate and Reward Time
Process End and Replace Technique
Programmer Expire and Revised Timescale
What type of diagram is this?
PERT
Dataflow diagram
Bar Chart
Gantt Chart
How long does it take to complete task F?
1 Month
3 Months
6 Months
8 Months