15 - Critical Path Analysis & Gantt Charts

Total questions: 8

Worksheet time: 6mins

Name
Class
Date
1.

Identify the longest task?

a)

Fill Kettle

b)

Boil Kettle

c)

Put tea in cup

d)

Put sugar in cup

e)

Get milk out of fridge

2.

How many milestones are there?

(a)  

3.

How many tasks are dependent on pouring water into a cup?

(a)  

4.

How many seconds form the critical path?

(a)  

5.

What is Critical Path Analysis

a)

A project management technique for process planning that defines critical (milestones) and non-critical tasks

b)

A graphical display of project activities represented by an area of land showing physical features

c)

A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site

d)

A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project

6.

What does PERT stand for?

a)

Project Evaluation and Review Technique

b)

Programme Estimate and Reward Time

c)

Process End and Replace Technique

d)

Programmer Expire and Revised Timescale

7.

What type of diagram is this?

a)

PERT

b)

Dataflow diagram

c)

Bar Chart

d)

Gantt Chart

8.

How long does it take to complete task F?

a)

1 Month

b)

3 Months

c)

6 Months

d)

8 Months