wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

TYPES OF CONTRACT IN CONSTRUCTION MANAGEMENT

Total questions: 12

Worksheet time: 11mins

Name
Class
Date
1.

What is Construction contract ?

a)

An exchange of promises between two or more parties to do, or refrain from doing an act, which resulting contract is enforceable in a court of law.

b)

A legal agreement document between two parties (client (Owner) & Contractor) that binds the contractor to do the job with the specified requirements and the client to pay for it.

c)

Exchange of money in return for construction material and building services.

d)

Buying from external organizations and 3rd parties to start construction project

2.

Which types of Contracts not used in Construction

a)

Design Build

b)

Unit price Contracts

c)

Lump-sum Contract

d)

Express and Implied Contracts

3.

The total cost of work in Unit Price Contract can be calculated

a)

After the sign the contract

b)

Before the sign the contract

c)

After the completion of the work

d)

Before the completion of the work

4.

Advantages of Unit price Contracts

a)

Tenderers prices are on exactly the same basis

b)

Owner does know the exact cost of the work.

c)

Avoid a lot of detailed accounting & measurement.

d)

Project scope and limits are defined prior to the start of construction.

5.

Which is not of disadvantages of Lump-sum Contract

a)

Plans & specifications must be every detail.

b)

Highly skilled Architect or Engineer is needed.

c)

The lack of time flexibility in this method may result in delayed project implementation.

d)

Plans & specifications do not need to be completed in detail

6.

Total cost of Cost Plus fixed fee Contract (CPFF)

a)

Total cost = Cost for the work X Fixed Fee

b)

Total cost = Cost for the work + Fixed Fee

c)

Total cost = Cost for the work + Percentage of cost

d)

Total cost = Cost for the work X Percentage

7.

In Cost plus incentive fee (CPIF) Contract, the compensation is based on contracting performance according to

a)

Budget

b)

Schedule

c)

Quality

d)

Budget, schedule and quality

8.

Advantage of Cost Plus Contract

a)

They allow the focus to shift from the overall cost to the on the quality of work being done.

b)

They may leave the final cost up in the air since they can't be predetermined.

c)

They may lead to a longer timeline for the project.

d)

The all risk on the contractor.

9.

Which sentence is true about Guaranteed Maximum Price (GMP) Contract

a)

The contractor agrees to perform work up a price ceiling.

b)

The contractor agrees to perform work within a price ceiling.

c)

This method gives greater flexibility for the contractor.

d)

All sentence not true

10.

In the Negotiated Contract The owner can negotiating with the contract including method of payment for the work, Bid, etc.

a)

True

b)

False

11.

In Design-Build Contracts is a method to deliver a project in which the design and construction services by the owner.

a)

True

b)

False

12.

Turn-key Contracts is a type of project that is constructed so that it could be sold to any buyer as a completed product

a)

True

b)

False